- Project category: Paved Roads
- Division: Division 5
- Status: In progress
Project Description
A Sturgeon County contractor, Central Civil Solutions, will be working on rehabilitating the subdivision roads in Woodridge. This project will upgrade the existing roads from gravel to a paved surface. Central Civil Solutions will deliver a notice of construction to the nearby residents in advance of construction.
Project Scope
The work will involve roadway reconstruction, granular base, asphalt paving, ditch work, culvert installations, clearing, and landscaping. The work will begin in Meadow Crescent and Woodridge Crescent, then move to Erickson Drive.
What this Means to You
Minor detours will be required throughout the project affecting the normal movement of traffic and pedestrians. During this time, there will be numerous personnel including subcontractors and heavy equipment in the construction zone. Please obey flaggers, detours, barricades, and traffic signs and drive safely through the area. Typical working hours are from 7 a.m. to 7 p.m. with long weekends off.
Related Documents
Updates
-
June 26, 2024: Construction underwayJune 26, 2024
Construction has started on this project. The contractor is currently stropping topsoil from Meadow Crescent.
-
June 12, 2024: Start date announcedJune 12, 2024
Construction is scheduled to start on June 17 and will last until mid-September, depending on the weather. The contractor is Central Civil Solutions. They will be distributing a notice of construction over the next few days.
-
March 6, 2024: Project page createdMarch 6, 2024