Construction Updates – September 2023

Transport Fibre (connects subdivisions, hamlets and industrial parks together)

  • Range Road 255 up to Highway 642 and Township Road 554 into Riviere Qui Barre are almost complete.
  • The highway segments east of Villeneuve are being worked on. Handholes and tie-ins are being finished up.
  • Crews will be down on Meadowview Drive after the Villeneuve east segments are completed.

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Fairhaven and West Fairhaven are 98% done.
  • Reyda Vista and the Airport are complete.
  • Silver Chief was started in late September, and is 45% complete.

Drop fibre (connects the access fibre to the premise)

  • Glory Hills is complete.
  • Riviere Qui Barre is 98% done
  • Fairhavens are 75% done.
  • Range Road 262 is 85% done.
  • Airport was started on Sept 18. It is currently 30% complete.
  • Heritage I.P., Northern Lights and Reyda Vista will be the next communities (in that order).

Splicing (connecting the fiber segments into one continuous length)

  • Transport section 2, going into Pine Sands is complete
  • Airport is complete, this area just requires drops.
  • Riviere Qui Barre, Reyda Vista and Heritage I.P are complete.
  • Fairhavens are 35% complete.

A fire advisory is in effect for Sturgeon County due to high temperatures and lack of precipitation.

Sturgeon County offices will be close Friday, April 18 and Monday, April 21 for the Easter weekend. Offices will re-open for regular business hours on Tuesday, April 22 from 8:30AM - 4:30PM.

Scroll to Top