Construction Updates – July 2023

Transport Fibre (connects subdivisions, hamlets and industrial parks together)

  • The transport segments west of Villeneuve are complete, and will be working in the East area of Villeneuve.
  • Transport crews are working their way from Villeneuve to Morinville performing drill shots as required.

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Range Road 262, Pine Sands and Glory Hills are almost complete. Fair Haven and West Fairhaven are in progress, crews will continue in these areas.
  • Villeneuve Airport – complete.

Drop fibre (connects the access fibre to the premise)

  • Pine Sands, Glory Hills and RQB are almost complete.
  • Crews will be in Villeneueve Airport next.
  • Cleanup work is happening in Calahoo and Shil Shol.

Splicing (connecting the fiber segments into one continuous length)

  • Currently working on the transport segment that connects West Country Hearth
  • Glory Hills is almsot complete.
  • Pine Sands will start next week